Welcome
to the page dedicated to our new home (show home)
offices
and shop.
located
in the Town of Wausau
When Bob and
Gloria Rybarczyk of Coldwell Bankers Action Realty found this lot, spring of 2017.
It was perfect
for us, in the Town of Wausau off Townline Rd.
Just outside
the City, in fact 6 ft of out back lot line and the north side lot line border Wausau
proper.
Surrounded by
mature pine, with the interior filled with lots and lots of Tag elders and alike.
And few small
good trees and small pines here and there.
It took many many
exhausting days just to cut in a road far enough to get truck of street.

Then we
installed the 30 foot culvert and flared ends (Per Town Rules). Making it a
uuuge driveway entrance, 30 foot being the width of your average town road.
Finaly gave
that up and rented a 773 BobCat with a forestry head.
With that we had
the lot cleaned up to this picture in one day.

A few more nights
and weekends of pilling up the resulting mulch and burning.

Was
then time for a drive way and we found that we had in excess of 16 inches of
topsoil. Being a wet year we ended up with allot of $ in a breaker rock to
ruffed in road. My excavation guys (Kurszewski Excavating, Mike and his guys)
also brought in sand for the shop/storage garage.
I had the house
drawn up the winter before we bought the land.
Once we were
looking seriously at lot laid out the lot and drew up the garage.

Our house is built on a hedonically heated slab with 2
inch foam insulation under R15. With
Fox Block ICF (insulating concrete form) frost wall and walls, that are R27+.
Triple pane windows, and Sun tubes Vs. sky lights. A huge
energy heal truss system 16" that allows for the thickest and highest R value one
can do all the way out over our 12" thick walls. This is the cross section drawing.
This system is
very much the greenest/sustainable/renewable way to build to date. We had a
Packers game with less then 20 people (we are all 98 Deg. heat plants) and had
to shut down heat, crack windows.
Changes we made that
are not depicted in layout areas follows. Laundry/mud room we added
cabinets. Packers room we added a service area and changed the 3/4 bath to a
built in shower and rearranged to fit. Oh and when we were setting trusses we
decided to add sun tubes to kitchen/dinning/formal living, great room vault.
On to building the
garage mid to late summer. The garage has it own power service and a full set of
stairs to the storage above. This is our storage basically you can think of it
as our basement. The down stairs then is Elite's shop heated by pellet stove and
an electric one car garage heater as backup.
Mike the Menards delivery guy has a jig for his boom to
set trusses. 
The full set of stairs to
storage room trusses ruffed in.
Poly on floor with top coat!
Drywall and finished
entire garage interior.
Around early
fall I started working on the side weekends we did not go north laying out
house. Generaly getting stuff on hand and prepping to dig and lay out footings.
Including the windows, as they go in poured cement walls I wanted to physicaly
be able to measure for the openings.
Fox
Blocks got delivered direct, except not all fit so Wes picked up the remainder
with his newly made trailer. I Mean by that made by hand by Wes. Using the axels
and A hitch from our old equipment trailers and fenders and other parts he made
at the Tech. See him proudly getting a pic of the maiden voyage.
Then around late
fall it was time to dig and start setting the box forms for the footings.
We found right away
there was just to much broken shall and bedrock to drive stakes. so we had to
use box forms and pack then in. But the house I'm thinking isn't going anywhere.
And then it was
time to pour.

By this time Mid to
end of November we were finishing up the last of the years projects and starting
to work a few days (both me and Wes) on the house. And it was time to set the
first (lift). That's 6 ft of the total 12 ft. of ICF wall and frost wall we were
doing, so poured in two lifts.
Time for the first lift!
Setting of the electric service pedestal
Then in our spare time again we put in the drainage to
grade for the Garage and flood stop drains.
Also wrapping the
house in DMX air gap membrane for drainage to keep things dry.
Then time to fill,
this is one of those things that makes this kind of house expensive. Unless you
can find the one lot (maybe) in the right place that is dead flat and yet just
at the top of a rise just the size of the house footprint. You will be filling
to the tune of 10-15K.

The race was on for
power. Day they set the pole we had snow.
Melted by the time the underground went in.

We set the rest of
the ICF walls, prepped the Bunking for windows. Poured the second lift and
installed the Ground breaker.
On November 11th, a
Saturday, I went and set the 3 season entrance posts... Yes all by my self.
As you can see by the pics it was all day and i was
burning daylight.
Trusses delivered we
set about getting the gable end trusses ready.
Were setting trusses
on December 8th and 9th.
Well drilled
Dec 18th.
Then we set about closing up the roof and installing
doors and windows.
I've not use tar
paper in 20 years.
The underlayment we use is good for 6 months and 60 mile an
hr winds all by itself. Properly cap nailed that is ! We roof come spring.
Wes went to Arizona
for Xmas and if you remember if went well below 0, so i took some time and did
just a bit. Got the fireplace in so I could start pumping heat in. And got
inside stuff we needed inside.
After the holidays with Wes back and a warm up we finished the valleys and caped
the chimney.

Right about then we
decided to do the Sun Tubes. Insulation where it was bats and plastic as
electrical went in above the ceiling. Then it was getting toasty and the inside
sand was thawing and sinking just a bit more!

We then brought in
10 yards of sand to level things back up after the final compacting, and
proceeded to hang the drywall. Finish the tube lights and blown insulation
in the remainder of the roof (the flat areas) and a bit over the R38 bats in the
vault. Running the rest of the in floor to grade drains. Running the underground
plumbing, gas and one electric line for island too.
It was at this time I took a weekend off. It was 7 Deg
Saturday night and 9 Degrees Sunday night. Yet the place is so energy efficient
that with just a electric one car garage heater going it was 48 deg inside an
open area of 3500 or so sq ft, when I got there Monday at 7AM.
Next was to flatten
the sand, lay down 6 mill plastic (best way to prevent Radon...). Then put down
2" insulation and prepped the in floor tub and 4 Seasons came and laid out the
in floor hydronic heat runs.

Time to pour floor.
We set up one pour each day, bull float, finish floated then hand
troweled. Then the next day formed up for the next and went over the previous
pour to scrape with a 20 grit rub brick. Best not to use a power trowel if you
want it flat as possible. And we did, as we used glue down vinyl planking and
poly on the garage floor. Every little dip and bump would show, every overlap
had to be scraped back flat and smooth. Every seam/transition from one to the
next had to be perfect.

Next came building
the walls in-between the drywalled ceiling and the floor. You can see in the
pics before that we have the top plates in place. We then just carefully fasten
the green treated bottom plates (don't want to hit any hydronic lines) and then
fill in with studs for wall. Then the last of the in wall plumbing and
electrical goes in. Oh and the soffit in packer room and AC ducts. Hanging
drywall as we go, when we can close off area. also insulating for sound in
Master, Laundry, Baths and Packer room walls. Installing Hydronic unit, AC and
air to air as well.
We started mudding
inside and I was roofing outside in-between snows mid to end of March. First few
weeks in April were sanding, texture, primer and paint and poly garage floor.
Glass block windows in Master Bath.

So right about here
we got floor laid Went up north and got a call someone wanted to by our house.
Good offer with no contingencies and no inspections, but we had to be out in a
few weeks. Did I mentioned we had just started doing projects and had planed on
finishing one room at a time. Moving in slowly, and house would likely get
looked at after school lets out and sell before it starts again.
So it was off to the
races finishing the project we had started, finishing room by room as we moved
in. Oh ya and the well was drilled but not hooked up, and we did not have the
tank and mound. Luckily it dried up and we got the mound in the day before
closing. However he day of closing we had no water yet, so we went up to 5th
wheel for the night. Next day we had water but had to flush with bucket. The
next night we had a bath. It would be several weeks until we had the kitchen
counter tops, and a shower. I never realized how much cleaner one is showering
until I missed it for weeks. Not saying a bath is not nice....
The crux of it all
is that photos dry up as in a week after closing we had many commitments again.
what follows is just a bit of finishing as we go and interior finals.
Below are
final picks There will be more forthcoming.
Some are
Panoramic surround walk-a-rounds for Face book, but I compressed them for kind
of a 3D peripheral vision Pic Hope they work out.
Fireplace
3 season front entrance/porch
Formal Living,
Dinning, Kitchen with Island vaulted great room


Laundry mudroom main
coat closet
1/2 Bath - guest

Pantry
His and Hers office with separate entrance door.
Excersize room with
Guest Murphy Bed
Hallway with art for
our favorite places
,with lots of room for additions!
Master
Suit
Half
path/Master toilet closet

Master bath
with sunk in floor bath and glass block windows
W spacious
walk in shower with no threshold, and virtually flat floor. Rain shower and hand
held.

Master closet
And the master Bedroom with built in wardrobe cabinets.

If
this note is still here, then there's more finished pics yet to come! And
outside too.